Which two actions should you perform?

You have a Power Automate flow that processes files in a Microsoft SharePoint document library. The flow only needs to be run as required. You add steps to the flow to process the files.

Before leaving the office for the day, the manager must initiate the flow. The flow must not start processing files before 11:00 PM.

You need to configure the flow.

Which two actions should you perform? Each correct answer presents part of the solution. NOTE: Each correct selection is worth one point.
A . Add a recurrence trigger and configure to run daily at 11 00 PM.
B. Add a Condition action. If the time greater than 11:00 PM use a Terminate action prevent further processing.
C. Manually trigger the flow.
D. Add a Delay Until action and enter the timestamp for 11 00 PM.

Answer: C,D

Explanation:

Delay an action until a specific timestamp.

Note: The Microsoft Dataverse connector provides four ways to add wait conditions. Use these wait conditions when you need to delay processing in your flows until a particular condition is met.

✑ Postpone triggering the flow and the first action until a specific time: Wait condition using Postpone Until.

✑ Add a fixed delay before the next step.

✑ Delay an action until a specific timestamp.

✑ Delay an action until a specific event occurs.

Reference: https://docs.microsoft.com/en-us/power-automate/dataverse/wait-conditions

Latest PL-100 Dumps Valid Version with 86 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments