Which statement describes how Kanban Teams handle velocity in SAFe during PI Planning?
Which statement describes how Kanban Teams handle velocity in SAFe during PI Planning?
A . They need to estimate their velocity in story points
B. They use throughput as an indication of their velocity
C. They use cycle time because it is more objective and based on actual timestamps
D. They participate in scoring Business Value; however, they have a different measure than velocity
Answer: B
Explanation:
https://www.scaledagileframework.com/team-kanban/