What action should be taken on Relentless Improvement Backlog items from the Problem Solving Workshop?

What action should be taken on Relentless Improvement Backlog items from the Problem Solving Workshop?
A . Assign points or prioritization levels
B. Calculate for cost before continuing
C. Use as direct input into the PI Planning session that follows
D. Assign to the team best suited to solve

Answer: C

Explanation:

https://www.scaledagileframework.com/inspect-and-adapt/