Which should be done during the process Closing a Programme?

Which should be done during the process Closing a Programme?
A . Confirm that key stakeholders are satisfied with the improvements
B . Provide an opportunity to plan a post-project review
C . Identify the need for future assessment of benefit realization
D . Enable all outstanding risks to be closed

Answer: C

Latest MSPF Dumps Valid Version with 112 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments