Should include all possible constraints

Should include all possible constraintsA . Only 1 is trueB . Only 2 is trueC . Both land 2are trueD . Neither 1 or 2 is trueView AnswerAnswer: D

January 13, 2021 No Comments READ MORE +

Which is represented in a summary risk profile?

Which is represented in a summary risk profile?A . Category of risk responseB . Impact of an issueC . Likelihood of a riskD . Cause of a riskView AnswerAnswer: C

January 13, 2021 No Comments READ MORE +

tp commands are executed in the transport subdirectory (Please choose one correct answer)

tp commands are executed in the transport subdirectory (Please choose one correct answer)A . BinB . logC . BUFFERD . EPSE . COFILESView AnswerAnswer: A

January 12, 2021 No Comments READ MORE +

What does the ‘I’ stand for in POTI, the model that helps with Blueprint development?

What does the ‘I’ stand for in POTI, the model that helps with Blueprint development?A . InvestmentB . ImplementationC . InductionD . InformationView AnswerAnswer: D

January 12, 2021 No Comments READ MORE +

Include the costs for tools to track and report on progress,

Include the costs for tools to track and report on progress,A . Only 1 is trueB . Only 2 is trueC . Both 1 and 2 are trueD . Neither 1 or 2 is trueView AnswerAnswer: B

January 11, 2021 No Comments READ MORE +

Which is a description of a programme resource?

Which is a description of a programme resource?A . The objective of a programmeB . A process to control a programmeC . A logical grouping of projects within a programmeD . An input required by a programmeView AnswerAnswer: D

January 11, 2021 No Comments READ MORE +

Aligns the programme with corporate strategy

Aligns the programme with corporate strategyA . Only 1 is trueB . Only 2 is trueC . Both 1 and 2 are trueD . Neither 1 or 2 is trueView AnswerAnswer: D

January 11, 2021 No Comments READ MORE +

Which is a governance theme?

Which is a governance theme?A . Identifying a ProgrammeB . Planning and ControlC . Risk Management CycleD . Managing the TranchesView AnswerAnswer: B

January 11, 2021 No Comments READ MORE +

Which is an outcome?

Which is an outcome?A . Product developed by a projectB . Measured operational improvementC . Products transitioned into live useD . New service ready for handoverView AnswerAnswer: C

January 10, 2021 No Comments READ MORE +

Which information is included in Benefit Profiles?

Which information is included in Benefit Profiles?A . Scheduled reviewsB . Dependent capabilitiesC . Procedures to avoid double countingD . Information audit requirementsView AnswerAnswer: B

January 10, 2021 No Comments READ MORE +