Which settings have to be made for this?

You want to use capacity availability checks for production orders .

Which settings have to be made for this?
A . A checking rule must be assigned in the checking control
B. The PRT Availability Check must be set in the checking control.
C. An overall profile must be assigned in the checking control.
D. The Relevant for Finite Scheduling indicator must be set

Answer: C,D