Which process goal is most likely to offer potential techniques to address this?
Your team wants to work in an Agile manner and has been asked to provide a cost estimate for the project even though management recognizes that the requirements will evolve overtime.
Which process goal is most likely to offer potential techniques to address this?
A . Project Management
B. Plan the Release
C. Explore Scope
D. Address Changing Stakeholder Needs
Answer: C