Which of the following would NOT be a common metric used for monitoring test preparation and execution?

Which of the following would NOT be a common metric used for monitoring test preparation and execution?
A . Number of Test cases passed and failed
B . Percentage of planned test cases designed
C . Number of test plan review comments
D . Percentage of tasks complete in test environment preparation

Answer: B