Which of the following should the IS auditor review FIRST?
An IS auditor notes the transaction processing times in an order processing system have significantly increased after a major release.
Which of the following should the IS auditor review FIRST?
A . Capacity management plan
B. Training plans
C. Database conversion results
D. Stress testing results
Answer: D