Which of the following risk mitigation strategies involves the execution of controls to reduce the risk factor and bring it to an acceptable level, or accepts the potential risk and continues operating the IT system?

Which of the following risk mitigation strategies involves the execution of controls to reduce the risk factor and bring it to an acceptable level, or accepts the potential risk and continues operating the IT system?
A . Risk assumption
B . Risk planning
C . Risk transference
D . Risk avoidance

Answer: A