Which of the following parameters can you model to plan production with extra shift(s)?

You are working on a mid-range plan that spans the seasonal peak and you are evaluating the need for additional crewing .

Which of the following parameters can you model to plan production with extra shift(s)?
A . Incremental production values
B . Capacity expansion with additional costs
C . Production source validity at the start of seasonal peak
D . Adjusted production interactive values

Answer: B