Which of the following is the first step that should be performed when establishing a disaster recovery plan?

Which of the following is the first step that should be performed when establishing a disaster recovery plan?
A . Agree on the goals and objectives of the plan
B . Determine the site to be used during a disaster
C Demonstrate adherence to a standard disaster recovery process
C . Identity applications to be run during a disaster

Answer: A

Explanation:

The first step that should be performed when establishing a disaster recovery plan is to agree on the goals and objectives of the plan. The goals and objectives of the plan should define what the plan aims to achieve, such as minimizing downtime, restoring critical functions, ensuring data integrity, or meeting compliance requirements. The goals and objectives of the plan should also be aligned with the business needs and priorities of the organization and be measurable and achievable.

Latest CS0-003 Dumps Valid Version with 128 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments