Which of the following is a project planning methodology that involves a complex series of required simulations to provide information about schedule risk?

CORRECT TEXT

Which of the following is a project planning methodology that involves a complex series of required simulations to provide information about schedule risk?
A . Monte Carlo Analysis.
B . Project Management Information System (PMIS).
C . Earned Value Management (EVM).
D . Integrated Project Plan

Answer: A