Which of the following BEST describes a release train?

Which of the following BEST describes a release train?
A . A set of interconnected software development activities that have to be executed in sequence due to object and resource dependencies
B. A powerful command me tool dedicated for migrating changes or metadata between environments and intended for use by DevOps engineers
C. It is a preplanned time frame and set of delivery activities that have been stringently planned into phases the individual teams must align with.
D. It is a form of a prerelease deployment validation method where third-parry systems require integration testing and load testing to be performed.

Answer: C