Which ADM phase starts with the receipt of a Request for Architecture Work from the sponsoring organization?

Which ADM phase starts with the receipt of a Request for Architecture Work from the sponsoring organization?
A . Phase A
B . Phase B
C . Phase H
D . Preliminary Phase
E . Requirements Management

Answer: A