In which ADM phase is the Implementation and Migration Plan coordinated with other frameworks?

In which ADM phase is the Implementation and Migration Plan coordinated with other frameworks?
A . Phase A
B . Phase E
C . Phase F
D . Phase G
E . Phase H

Answer: C