Which action resolves the problem?

Refer to the exhibit.

An engineer must connect N2K-Fex-1 and N5K-Core-1 so that the traffic flow between the two devices uses load balancing. After inspecting the statistics of the interconnecting interfaces, the engineer concludes that only one link is used.

Which action resolves the problem?
A . Configure source-destination load balancing on N5K-Core-1.
B . Configure each uplink to be a member of a separate LACP port channel.
C . Configure the pinning max-link as 2.
D . Configure destination-mac load balancing on N5K-Core-1

Answer: C

Explanation:

https://www.cisco.com/c/m/en_us/techdoc/dc/reference/cli/n5k/commands/pinning-max-links.html