When using the dispatcher workspace integration with dynamic scheduling, if a dispatcher drags a lower priority task over a higher priority task, what will occur?
When using the dispatcher workspace integration with dynamic scheduling, if a dispatcher drags a lower priority task over a higher priority task, what will occur?
A . Both tasks are automatically- reassigned
B . Both tasks are automatically assigned
C . A warning is displayed and dispatcher confirmation is required
D . The higher priority task is automatically reassigned
Answer: C