What is the default schedule for a project?

What is the default schedule for a project?
A . 8-hour workday (from 8 to 12 and 1 to 5).
B . 8-hour workday (from 9 to 12 and 1 to 6).
C . 9-hour workday (from 8 to 12 and from 1 to 5).
D . 8-hour workday (from 9 to 5).

Answer: A