What is the correct order of steps to expand a Dell Power Edge based V>Rail Cluster?

What is the correct order of steps to expand a Dell Power Edge based V>Rail Cluster?

Answer:

Latest DES-6321 Dumps Valid Version with 103 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
1 Comment
Inline Feedbacks
View all comments
DHIRAJ HARSHE
DHIRAJ HARSHE
3 years ago

The correct answer is below
Step1 = Power on the new VxRail node
Step2 = Verify that the Loudmouth service is running
Step3 = Connect to the vSphere Client 
Step4 = Verify that the new VxRail node has been discovered
Step5 = Add the new node to the existing Cluster