What is one way to ensure a team is holding successful Iteration Reviews and demos?

What is one way to ensure a team is holding successful Iteration Reviews and demos?
A . The team demos working functionality
B . The team swarms to prepare for demos
C . The team shares improving metrics
D . The team ensures they complete every Story

Answer: A

Explanation:

One way to ensure a team is holding successful iteration reviews and demos is to have the team demo working, tested system components that meet the definition of done (DoD). This shows the team’s progress and value delivery, and allows them to receive feedback from the product owner and other stakeholders. The team should minimize the use of slides and the preparation time for the demos, and focus on the solution instead of the presentation. The team should also discuss the impact of the current solution on the nonfunctional requirements (NFRs) and identify any risks or

impediments.

Reference: Iteration Review – Scaled Agile Framework

Exam Study Guide: SSM (6.0) – SAFe® Scrum Master

Latest SSM Dumps Valid Version with 204 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments