What does the Scrum Team do with Product Backlog items that weren’t completed, or done, in the Sprint?

What does the Scrum Team do with Product Backlog items that weren’t completed, or done, in the Sprint?
A . Put it on the Product Backlog for the Product Owner to decide what to do with it
B. Do not include the item in the Increment this Sprint
C. If the stakeholders agree, the Product Owner can accept it and release it to the users
D. Review the item, add the “Done” part of the estim te to the velocity and create a Story for the remaining work.

Answer: A,B

Explanation:

Scrum Guide:

Work cannot be considered part of an Increment unless it meets the Definition of Done.

The moment a Product Backlog item meets the Definition of Done, an Increment is born.

If a Product Backlog item does not meet the Definition of Done, it cannot be released or even presented at the Sprint Review. Instead, it returns to the Product Backlog for future consideration.

Latest PSM III Dumps Valid Version with 62 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments