What are the best responses?

A Project Manager working with your Scrum Team has raised concerns about progress and money spent.

What are the best responses? (choose all that apply)
A . Scrum doesn’t have Project Managers so disregard their concerns
Promote transparency by sharing the Product Backlog and ensuring the Project Manager has access
Show the Earned Value Analysis (EVA) report
Share the last stakeholder briefing document prepared by the Product Owner
Have a discussion with the Project Manager; share the current impediments and forecast for the Sprint

Answer: B,E

Explanation:

Scrum Guide:

The Product Owner is also accountable for effective Product Backlog management, which includes:

– Developing and explicitly communicating the Product Goal;

– Creating and clearly communicating Product Backlog items;

– Ordering Product Backlog items; and,

– Ensuring that the Product Backlog is transparent, visible and understood.

Every organization has its own structure, perhaps, some has the Project Manager role, if this is the case and this role has interest or touchpoints with the Scrum project, the Product Ownes is accountable for providing the necessary information.