What is an input to the Program Increment Planning process that highlights how Product Management plans to accomplish the Vision?

What is an input to the Program Increment Planning process that highlights how Product Management plans to accomplish the Vision?A . Top ten Features B. Business context C. Program boardView AnswerAnswer: A Explanation: Read more: https://www.scaledagileframework.com/pi-planning/

May 11, 2023 No Comments READ MORE +

Communicating the Vision to the Agile Release Train during Program Increment Planning supports which SAFe Core Value?

Communicating the Vision to the Agile Release Train during Program Increment Planning supports which SAFe Core Value?A . Program Execution B. Alignment C. TransparencyView AnswerAnswer: B Explanation: Read more: https://www.scaledagileframework.com/safe-core-values/

May 11, 2023 No Comments READ MORE +

What are two different types of Enabler Stories? (Choose two.)

What are two different types of Enabler Stories? (Choose two.)A . Exploration B. Infrastructure C. Security D. AutomationView AnswerAnswer: A,B Explanation: Read more: https://www.scaledagileframework.com/enablers/

May 11, 2023 No Comments READ MORE +

other Product Owners, and who else?

During Program Increment Planning, the Product Owner coordinates primarily with their Agile Team, other Product Owners, and who else?A . The System Architect/Engineer B. The Solution Train Engineer C. Product ManagementView AnswerAnswer: C Explanation: Read more: https://www.scaledagileframework.com/product-management/, https://www.scaledagileframework.com/product-owner/

May 11, 2023 No Comments READ MORE +

What is one way in which the SAFe House of Lean might influence a Product Owner?

What is one way in which the SAFe House of Lean might influence a Product Owner?A . Help Agile Teams gain a clear understanding of their Customers B. Defer improvements so that the team can spend more time creating Stories C. Develop Roadmaps that guide future activitiesView AnswerAnswer: A Explanation:...

May 11, 2023 No Comments READ MORE +

What does assigning business value to a team's PI Objectives influence?

What does assigning business value to a team's PI Objectives influence?A . How teams plan the implementation B. How the Kanban work in process limits are set C. How to achieve objectivesView AnswerAnswer: A Explanation: Read more: https://www.scaledagileframework.com/pi-objectives/

May 10, 2023 No Comments READ MORE +

Which role in SAFe typically has the most direct access to customers?

Which role in SAFe typically has the most direct access to customers?A . Product Owner (PO) B. Release Train Engineer (RTE) C. Product Management (PM)View AnswerAnswer: A Explanation: Read more: https://www.scaledagileframework.com/product-owner/

May 10, 2023 No Comments READ MORE +

What are the minimum requirements for a Feature?

What are the minimum requirements for a Feature?A . X Name, benefit hypothesis, and acceptance criteria B. Whatever the Agile Release Train determines is required C. Benefit hypothesis, acceptance criteria, and priorityView AnswerAnswer: A Explanation: Read more: https://www.scaledagileframework.com/features-and-capabilities/

May 10, 2023 No Comments READ MORE +

When should a dependency be raised as a program risk?

When should a dependency be raised as a program risk?A . When it must be accepted B. When an Enabler can fix itqueja C. When it can be resolvedView AnswerAnswer: A Explanation: Read more: https://www.scaledagileframework.com/pi-planning/

May 10, 2023 No Comments READ MORE +

What is the purpose of a Program Epic?

What is the purpose of a Program Epic?A . To align Strategic Themes to portfolio investments B. To capture Agile Release Train initiatives that cannot be completed in a single Program Increment C. To aligning multiple Agile Release Trains to a common objectiveView AnswerAnswer: B Explanation: Read more: https://www.scaledagileframework.com/program-and-solution-kanbans/

May 10, 2023 No Comments READ MORE +