Which of the following factors will MOST likely influence the communication methods used in the project?

A project team is mainly based in a metropolitan area. The team also has members in a remote area, where Internet access is limited and unstable. Which of the following factors will MOST likely influence the communication methods used in the project?A . Personal preferencesB . Technological factorsC . Language...

August 8, 2022 No Comments READ MORE +

Which of the following should the project manager do NEXT?

The project manager for a TV tower construction project receives notification that a strong storm is expected the following week. Which of the following should the project manager do NEXT?A . Evaluate the risk, inform major stakeholders about the problem, and issue a change request immediately.B . Evaluate the risk,...

August 8, 2022 No Comments READ MORE +

Assuming an iterative approach, which of the following will be conducted at the end of each iteration?

Assuming an iterative approach, which of the following will be conducted at the end of each iteration?A . SCRUM retrospectiveB . Kickoff meetingC . Budget baselineD . Risk reviewView AnswerAnswer: A Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 306

August 8, 2022 No Comments READ MORE +

Which of the following should a project manager update to document this information?

A team lead informs the project manager that the datacenter will not be accessible when the project needs to be completed. The team lead also indicates that the team member who is assigned to complete the datacenter project is out on medical leave. Which of the following should a project...

August 7, 2022 No Comments READ MORE +

In which of the following documents can this information be found?

A project manager needs to identify the resources assigned to a particular task. In which of the following documents can this information be found?A . Project scheduleB . Cost planC . Scope statementD . Impact assessmentView AnswerAnswer: A Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis,...

August 7, 2022 No Comments READ MORE +

Which of the following effects is this MOST likely to have on the project?

A new project sponsor has joined the project team, and the constraints on the project have been reprioritized. The project cost was previously the most important factor, but the new sponsor has indicated that meeting a new, shorter deadline is the priority. Which of the following effects is this MOST...

August 7, 2022 No Comments READ MORE +

Which of the following would be the MOST beneficial?

A project manager is attempting to establish the proper sequencing and duration of project activities. Which of the following would be the MOST beneficial?A . Network diagramB . Ishikawa diagramC . WBSD . Gantt chartView AnswerAnswer: A Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017,...

August 7, 2022 No Comments READ MORE +

Which of the following should have occurred to prevent this issue?

During the execution phase, the project manager discovered that the testing phase is dependent on completion of the vendor’s tasks. The project team has just informed the project manager their activities are almost complete, and they would like permission to begin testing. The vendor is not scheduled to deliver the...

August 7, 2022 No Comments READ MORE +

Which of the following tools is MOST appropriate for the project team to use to determine the cause of the problem?

One deliverable failed during testing, and this has already happened several times. Which of the following tools is MOST appropriate for the project team to use to determine the cause of the problem?A . Run chartB . Fishbone diagramC . Scatter diagramD . Gantt chartView AnswerAnswer: B Explanation: References: Kim...

August 7, 2022 No Comments READ MORE +

Which of the following is the primary purpose of an MOA or an MOU?

Which of the following is the primary purpose of an MOA or an MOU?A . State expectations of all signatory parties to reduce potential misunderstandings.B . Facilitate potential legal action and resulting remediation if one of the signatory parties violates any terms.C . Enumerate a detailed code of conduct for...

August 7, 2022 No Comments READ MORE +