Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete?

During the execution phase of a project, a project task has run longer than anticipated. Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete?A . 12 daysB . 14 daysC . 16 daysD . 19 daysView AnswerAnswer:...

August 9, 2022 No Comments READ MORE +

Which of the following should a project manager update to document this information?

A team lead informs the project manager that the datacenter will not be accessible when the project needs to be completed. The team lead also indicates that the team member who is assigned to complete the datacenter project is out on medical leave. Which of the following should a project...

August 9, 2022 No Comments READ MORE +

Which of the following is the FIRST step the project manager should take?

A carpenter on a project team reports there is insufficient time to accomplish tasks on schedule. Which of the following is the FIRST step the project manager should take?A . Assess the risk register’s new items.B . Review the task start and finish dates.C . Obtain additional resources.D . Analyze...

August 9, 2022 No Comments READ MORE +

Which of the following is MOST likely to be the first document created by the project manager?

A vendor has accepted a proposed project from a customer. Which of the following is MOST likely to be the first document created by the project manager?A . Project charterB . Project management planC . Project statement of workD . Project scheduleView AnswerAnswer: C Explanation: References: Kim Heldman, CompTIA Project+...

August 9, 2022 No Comments READ MORE +

Which of the following actions should the project manager take?

During a project assessment, a project manager determines the initial project cost estimates were incorrect, and there is not enough budget left, including reserves, to complete the project. Which of the following actions should the project manager take?A . Alert the project sponsor of the situation.B . Contact the customer...

August 8, 2022 No Comments READ MORE +

Which of the following describes how the project manager should BEST determine the initial sequence and durations?

After identifying all known tasks, the project manager has started to sequence and set durations. Which of the following describes how the project manager should BEST determine the initial sequence and durations?A . Use milestones identified in the project charter.B . Use data based on past knowledge.C . Hold a...

August 8, 2022 No Comments READ MORE +

Which of the following is a characteristics of a matrix organization?

Which of the following is a characteristics of a matrix organization?A . Authority lies solely with the project manager.B . Authority is directed by the project architect.C . Authority is shared between the project manager and project coordinator.D . Authority is shared between functional and project managers.View AnswerAnswer: D Explanation:...

August 8, 2022 No Comments READ MORE +

Which of the following is the BEST way for the project manager to address the issue?

A project manager is unsure if the quality of a deliverable from a SME meets specifications. Which of the following is the BEST way for the project manager to address the issue?A . Conduct a face-to-face or telephone meeting with the team member.B . Send an email outlining the concerns...

August 8, 2022 No Comments READ MORE +

In which of the following phases is the project?

A project manager is creating the WBS. In which of the following phases is the project?A . InitiationB . PlanningC . ExecutionD . ClosingView AnswerAnswer: B Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 139

August 8, 2022 No Comments READ MORE +

Which of the following is the MOST effective method for providing these updates?

A project requires daily status updates. Which of the following is the MOST effective method for providing these updates?A . BacklogB . StandupC . KickoffD . RetrospectiveView AnswerAnswer: B Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 306

August 8, 2022 No Comments READ MORE +