Which of the following would the project manager MOST likely do?

A project team member highlights to the project manager that expensive licensing for critical software in use across the project may expire before the completion project. Which of the following would the project manager MOST likely do?A . Place a risk on the risk register and arrange a risk review...

September 2, 2021 No Comments READ MORE +

Which of the following should the project manager do NEXT?

A project in the execution phase is over budget, and tasks on the critical path are on schedule. Which of the following should the project manager do NEXT?A . Update the project management plan.B . Issue a change request.C . Revise the project charter.D . Evaluate the impact to the...

September 1, 2021 No Comments READ MORE +

In which of the following categories does a business process change fit?

In which of the following categories does a business process change fit?A . Project changeB . Organizational changeC . General changeD . Departmental changeView AnswerAnswer: B Explanation: “Business process changes typically occur within the organization. An example of a business process change is automating a process that previously was performed...

September 1, 2021 No Comments READ MORE +

Which of the following should the project manager do FIRST?

A team member was replaced on a project by a new team member of equal capability. Which of the following should the project manager do FIRST?A . Resource loadingB . Resource levelingC . Prioritizing tasksD . Allocating resourcesView AnswerAnswer: D

August 31, 2021 No Comments READ MORE +

In a project with a of $235,000, the CPI is 0.80, and the SPI is 1.20. Based on this information, which of the following can the key stakeholders determine about the project?

In a project with a of $235,000, the CPI is 0.80, and the SPI is 1.20. Based on this information, which of the following can the key stakeholders determine about the project?A . The project is under budget and ahead of schedule.B . The project is over budget and ahead...

August 31, 2021 No Comments READ MORE +

Which of the following is the primary purpose of an MOA or an MOU?

Which of the following is the primary purpose of an MOA or an MOU?A . State expectations of all signatory parties to reduce potential misunderstandings.B . Facilitate potential legal action and resulting remediation if one of the signatory parties violates any terms.C . Enumerate a detailed code of conduct for...

August 31, 2021 No Comments READ MORE +

A project has been experiencing some difficulties due to third-party vendors. The project manager should request.

A project has been experiencing some difficulties due to third-party vendors. The project manager should request.A . Additional resourcesB . A gate reviewC . A risk register updateD . A performance auditView AnswerAnswer: C Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 272

August 31, 2021 No Comments READ MORE +

Which of the following represents the number of days the project schedule will be delayed?

A part that is needed to complete Task 3 has been backordered and will arrive three days later than scheduled. Task 3 must be complete for Task 4 to start. There is one day of float for the two tasks. Which of the following represents the number of days the...

August 31, 2021 No Comments READ MORE +

Which of the following is the MOST cost-effective step to take to ensure the project’s success?

A project manager was directed to complete a project sooner than previously planned. Which of the following is the MOST cost-effective step to take to ensure the project’s success?A . Reduce the scopeB . Increase the budgetC . Decrease staffD . Update the WBSView AnswerAnswer: D Explanation: References: https://books.google.co.za/books?id=evR0gPFBHJ4C&pg=PA128&lpg=PA128&dq=complete+a+project+sooner+-+update+WBS&source=bl&ots=O650UKpUEK&sig=mlexbBmFJKkAuXuftqO2YjLLOgo&hl=en&sa=X&ved=0ahUKEwi8uJXIj_DXAhUKuRQKHW3fDKAQ6AEIMTAC#v=onepage&q=complete%20a%20project%20sooner%20-%20update%20WBS&f=false

August 30, 2021 No Comments READ MORE +

Which of the following constraints does this impact MOST?

A non-stakeholder approaches the project manager and asks if certain items can be added to a project that was started two months earlier. Which of the following constraints does this impact MOST?A . TimeB . ScheduleC . ScopeD . CostView AnswerAnswer: D

August 30, 2021 No Comments READ MORE +