Which of the following documents should the project team reference to fast-track the project?

A program manager informs a project manager that a new, high-priority project has been approved and will need the current project’s resources before the scheduled project close date. The project team meets and determines that the project should be fast-tracked. Which of the following documents should the project team reference...

September 5, 2021 No Comments READ MORE +

This type of analysis is an example of which of the following?

The project manager is reviewing the earned value of work completed compared to the planned value and is representing it in a dollar figure. This type of analysis is an example of which of the following?A . Cost performance indexB . Risk mitigationC . Schedule varianceD . Cost varianceView AnswerAnswer:...

September 5, 2021 No Comments READ MORE +

Which of the following describes risk mitigation?

Which of the following describes risk mitigation?A . The transfer of the risk to another entity or project inside or outside the organization, along with associated costs.B . The understanding of the risk with a detailed explanation of how the project intends to address the potential for occurrence.C . The...

September 5, 2021 No Comments READ MORE +

Which of the following documents could help in this situation?

A team member was assigned a new task during a meeting. The team member did not complete the task by the end of the phase, and the PM is looking for evidence to escalate the issue. Which of the following documents could help in this situation?A . Issue logB ....

September 5, 2021 No Comments READ MORE +

Given the attached chart, which of the following is the critical path if one day is added to each task for quality control?

During a project, the project manager discovers there is insufficient time allotted for quality control. The project manager prepared to submit a revised schedule to the CCB. Given the attached chart, which of the following is the critical path if one day is added to each task for quality control?A...

September 5, 2021 No Comments READ MORE +

Which of the following should the project manager do to obtain the resources?

The project sponsor has cut the resources required for project completion. The project manager cannot complete the project without additional resources. Which of the following should the project manager do to obtain the resources?A . The project manager should identify and document the reasons for the additional resources in a...

September 5, 2021 No Comments READ MORE +

Which of the following roles has approval authority for project funding?

Which of the following roles has approval authority for project funding?A . ChampionB . Chief Financial Officer (CFO)C . Project Management Office (PMO)D . SponsorView AnswerAnswer: D Explanation: References https://books.google.com.pk/books?id=scjmDQAAQBAJ&pg=PA29&lpg=PA29&dq=comptia+roles+has+approval+authority+for+project+funding&source=bl&ots=QjPXRQ0G3Y&sig=gToYb55ruudpdmlyclTUJwsS7vY&hl=en&sa=X&ved=0ahUKEwiA08WQ3IXbAhWJpo8KHe97ACMQ6AEIRjAD#v=onepage&q=comptia%20roles%20has%20approval%20authority%20for%20project%20funding&f=false

September 4, 2021 No Comments READ MORE +

Which of the following tools should the project team select to determine the possible origins of the increased costs?

A team has been assembled and assigned a project to reduce recent, unanticipated production cost overruns. Which of the following tools should the project team select to determine the possible origins of the increased costs?A . Pareto chartB . Fishbone diagramC . Process diagramD . Run chartView AnswerAnswer: B

September 4, 2021 No Comments READ MORE +

A project manager is trying to ensure the quality of the design and reduce the number of potential defects. The project manager would like to use the fishbone diagram to perform this analysis.

A project manager is trying to ensure the quality of the design and reduce the number of potential defects. The project manager would like to use the fishbone diagram to perform this analysis. This type of modeling relies on:A . Prioritizing the specific event.B . Variance in the process over...

September 4, 2021 No Comments READ MORE +

Which of the following steps should the project manager perform NEXT?

A project manager has been assigned a project with a budget of $50,000. Three change requests are submitted during execution that will increase the overall project cost to $60,000. Which of the following steps should the project manager perform NEXT?A . Wait until the change requests are approved by the...

September 4, 2021 No Comments READ MORE +