Which of the following documents should the potential vendors submit so the project manager can find the best vendors for the project?

A project manager would like to bring vendors into a new project. Which of the following documents should the potential vendors submit so the project manager can find the best vendors for the project?A . SLAB . SOWC . Change requestD . RFPView AnswerAnswer: B Explanation: Explanation “If you’re working...

September 6, 2021 No Comments READ MORE +

Which of the following factors will MOST likely influence the communication methods used in the project?

A project team is mainly based in a metropolitan area. The team also has members in a remote area, where Internet access is limited and unstable. Which of the following factors will MOST likely influence the communication methods used in the project?A . Personal preferencesB . Technological factorsC . Language...

September 6, 2021 No Comments READ MORE +

Which of the following documents should the project manager create?

A project manager is assigned to a new project that must start immediately. No formal or approved documents have been authored for the project. The project manager must identify project roles, justify the business need, and determine project scope boundaries. Which of the following documents should the project manager create?A...

September 6, 2021 No Comments READ MORE +

Which of the following would be the MOST effective means to do this?

The project team is distributed throughout a single country. The scrum master has decided to hold remote "stand-ups" on a daily basis. Which of the following would be the MOST effective means to do this?A . Instant messagingB . Video conferenceC . Phone callD . Collaboration websiteView AnswerAnswer: B

September 6, 2021 No Comments READ MORE +

Which of the following describes how a project is related to a program?

Which of the following describes how a project is related to a program?A . A program is a combination of multiple projects.B . A program contains an element of the project.C . A program is a part of a project.D . A program uses half of the project’s budget.View AnswerAnswer:...

September 6, 2021 No Comments READ MORE +

Which of the following effects is this MOST likely to have on the project?

A new project sponsor has joined the project team, and the constraints on the project have been reprioritized. The project cost was previously the most important factor, but the new sponsor has indicated that meeting a new, shorter deadline is the priority. Which of the following effects is this MOST...

September 6, 2021 No Comments READ MORE +

Which of the following charts is a graphical representation of the causes of a specific event?

Which of the following charts is a graphical representation of the causes of a specific event?A . HistogramB . ScatterC . FishboneD . GanttView AnswerAnswer: C Explanation: Explanation A fishbone diagram is a cause-and-effect diagram that shows the relationship between the effects of problems and their causes. This diagram depicts...

September 6, 2021 No Comments READ MORE +

Which of the following job roles is primarily tasked with communicating the project timeline changes?

Which of the following job roles is primarily tasked with communicating the project timeline changes?A . Project schedulerB . Project managerC . Project sponsorD . Project coordinatorView AnswerAnswer: B Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 93

September 6, 2021 No Comments READ MORE +

Which of the following factors is the MOST likely cause for this scenario?

The project manager of a global project constantly receives complaints from individuals at another location that some team members are not available after lunch on Fridays. This is acceptable to the project manager. Which of the following factors is the MOST likely cause for this scenario?A . Personal preferenceB ....

September 5, 2021 No Comments READ MORE +

Based on this information, the CPI reflects which of the following about the project?

A project manager is creating the monthly report for top management. The project manager has collected the information below: AC = 100 PV = 80 EV = 120 Based on this information, the CPI reflects which of the following about the project?A . It is under budget.B . It is...

September 5, 2021 No Comments READ MORE +