Which of the following is the project manager facing?
A project manager travels abroad to meet the offshore team and sends out a meeting invitation to review requirements. However, many team members decline the meeting invitation. The PM approaches one team member to determine why people are declining. The team member indicates the project manager scheduled the meeting at...
Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete?
During the execution phase of a project, a project task has run longer than anticipated. Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete?A . 12 daysB . 14 daysC . 16 daysD . 19 daysView AnswerAnswer:...
The PMO is responsible for: (Choose two.)
The PMO is responsible for: (Choose two.)A . managing the project plan, scope, risk, and budget.B . contributing expertise, deliverables, and estimates of costs.C . setting standards and practices for the organization and providing governance.D . outlining consequences of non-performance and coordinating between disparate projects.E . approving funding, developing the...
Which of the following were MOST likely missed during project planning?
A department manager asks a project manager about the status of a project that has only a few employees from the department assigned to it. Which of the following were MOST likely missed during project planning?A . Issue log and process diagramB . Resource analysis and Gantt chartC . Stakeholder...
Which of the following is the MOST expedient communication method, assuming the question can be resolved quickly?
A project team is composed of numerous team members who are located throughout a country. All personnel have identified core business hours. A team engineer based in a machine shop has a question during business hours for the project manager, who is located at a different facility. Which of the...
Which of the following should the project manager do NEXT?
A project manager received a change request, immediately documented the required changes, and evaluated the impact of and justification for the changes. Which of the following should the project manager do NEXT?A . Gain approval for the changes.B . Identify the approval authority.C . Implement the changes.D . Create an...
Which of the following metrics demonstrates to a project manager if a project is overspending or underspending?
Which of the following metrics demonstrates to a project manager if a project is overspending or underspending?A . EACB . BACC . CPID . ETCView AnswerAnswer: C Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 231
Which of the following would BEST communicate the need for a WBS to the other managers?
A project manager wants to introduce the practice of a WBS to the PMO, but the other managers believe this will create extra work. Which of the following would BEST communicate the need for a WBS to the other managers? (Select TWO).A . Using the WBS will help prevent work...
Which of the following is the MOST effective method for providing these updates?
A project requires daily status updates. Which of the following is the MOST effective method for providing these updates?A . BacklogB . StandupC . KickoffD . RetrospectiveView AnswerAnswer: B Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 306
In which of the following components of the project plan should this be documented?
A project has just finished performance testing and found that the application can only handle 100 concurrent users where the requirement was to handle 500 concurrent users. In which of the following components of the project plan should this be documented?A . Scope statementB . Issues logC . WBSD ....