Which of the following is a characteristics of a matrix organization?
Which of the following is a characteristics of a matrix organization?A . Authority lies solely with the project manager.B . Authority is directed by the project architect.C . Authority is shared between the project manager and project coordinator.D . Authority is shared between functional and project managers.View AnswerAnswer: D Explanation:...
Which of the following is the NEXT step?
A project manager is justifying a required change with the associated impact on the project. Which of the following is the NEXT step?A . ImplementationB . ApprovalC . ValidationD . AuditingView AnswerAnswer: B Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 294
In which of the following organizational structures would a project manager have the MOST authority?
In which of the following organizational structures would a project manager have the MOST authority?A . ProjectizedB . Strong matrixC . Balanced matrixD . FunctionalView AnswerAnswer: A Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 57
Which of the following should be used to complete the tasks on time?
A project manager does not have enough time to complete several tasks on a critical path. The budget is a low concern. Which of the following should be used to complete the tasks on time?A . Fast-track the tasks.B . Utilize positive float.C . Crash the schedule.D . Remove the...
A project team has finished creating a WBS and started developing a schedule. The team should FIRST determine the:
A project team has finished creating a WBS and started developing a schedule. The team should FIRST determine the:A . durations.B . tasks.C . critical path.D . resources.View AnswerAnswer: B
Which of the following is the BEST project management methodology for this requirement?
A customer will have ongoing changes to project requirements. Which of the following is the BEST project management methodology for this requirement?A . WaterfallB . AgileC . PRINCE2D . Bottom-upView AnswerAnswer: B Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 310
Which of the following describes how a project is related to a program?
Which of the following describes how a project is related to a program?A . A program is a combination of multiple projects.B . A program contains an element of the project.C . A program is a part of a project.D . A program uses half of the project’s budget.View AnswerAnswer:...
A project has been experiencing some difficulties due to third-party vendors. The project manager should request.
A project has been experiencing some difficulties due to third-party vendors. The project manager should request.A . Additional resourcesB . A gate reviewC . A risk register updateD . A performance auditView AnswerAnswer: C Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 272
Which of the following factors will MOST likely influence the communication methods used in the project?
A project team is mainly based in a metropolitan area. The team also has members in a remote area, where Internet access is limited and unstable. Which of the following factors will MOST likely influence the communication methods used in the project?A . Personal preferencesB . Technological factorsC . Language...
Which of the following documents need to be updated as events occur during a project? (Select TWO).
Which of the following documents need to be updated as events occur during a project? (Select TWO).A . Change requestB . Risk registerC . Meeting minutesD . Issue logE . Status reportView AnswerAnswer: C,E