Which of the following elements should be included on a responsibility assignment matrix?
Which of the following elements should be included on a responsibility assignment matrix?A . Responsible, accountable, consulted, informedB . Resource, accountable, signoff, inputC . Responsible, accurate, confidential, informedD . Resource, accountable, consulted, informedView AnswerAnswer: A
Which of the following would be the MOST effective means to do this?
The project team is distributed throughout a single country. The scrum master has decided to hold remote "stand-ups" on a daily basis. Which of the following would be the MOST effective means to do this?A . Instant messagingB . Video conferenceC . Phone callD . Collaboration websiteView AnswerAnswer: B
Which of the following should the project manager notify?
A milestone task on the critical path has been completed. Which of the following should the project manager notify?A . Owner of predecessor taskB . Project teamC . Project sponsorD . Project steering committeeView AnswerAnswer: C
Which of the following should the project manager notify?
A milestone task on the critical path has been completed. Which of the following should the project manager notify?A . Owner of predecessor taskB . Project teamC . Project sponsorD . Project steering committeeView AnswerAnswer: C
Which of the following is described in this scenario?
During a project, a key stakeholder asks a project team member to add a requirement. The team member adds the requirement without informing the project manager. Which of the following is described in this scenario?A . Change requestB . Risk mitigationC . Change controlD . Scope creepView AnswerAnswer: D
Based on this information, the CPI reflects which of the following about the project?
A project manager is creating the monthly report for top management. The project manager has collected the information below: AC = 100 PV = 80 EV = 120 Based on this information, the CPI reflects which of the following about the project?A . It is under budget.B . It is...
Which of the following describes the project status?
The project schedule performance index is 1.1, and the cost performance index is 0.9. Which of the following describes the project status?A . Ahead of schedule and over budgetB . Behind schedule and under budgetC . Ahead of schedule and under budgetD . Behind schedule and over budgetView AnswerAnswer: C
Which of the following should the project manager notify?
A milestone task on the critical path has been completed. Which of the following should the project manager notify?A . Owner of predecessor taskB . Project teamC . Project sponsorD . Project steering committeeView AnswerAnswer: C
Considering the project has a CPI of 0.89 and an SPI of 1.14, and the approved ones will be implemented, which of the following should the project manager do LAST?
new stakeholder has been added to a project with a BAG of $850,000. The stakeholder has raised five change requests to the CCB; two of them have been approved, and three are awaiting initial review. Considering the project has a CPI of 0.89 and an SPI of 1.14, and the...
Which of the following should the project manager notify?
A milestone task on the critical path has been completed. Which of the following should the project manager notify?A . Owner of predecessor taskB . Project teamC . Project sponsorD . Project steering committeeView AnswerAnswer: C