Which of the following is a key aspect of the Agile project management methodology?
Which of the following is a key aspect of the Agile project management methodology?A . Test-drivenB . Daily standup meetingsC . Short project durationsD . Defined list of requirementsView AnswerAnswer: B Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 286
Which of the following are characteristics of a project? (Choose two.)
Which of the following are characteristics of a project? (Choose two.)A . OngoingB . TemporaryC . Start and finishD . Achieving a goalE . Consisting of milestonesF . Restricting the budgetView AnswerAnswer: B,C Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 27
Which of the following steps should the project manager perform NEXT?
A project manager has been assigned a project with a budget of $50,000. Three change requests are submitted during execution that will increase the overall project cost to $60,000. Which of the following steps should the project manager perform NEXT?A . Wait until the change requests are approved by the...
Which of the following is the FIRST document the protect manager should review?
A project manager is assigned to an ongoing project. Which of the following is the FIRST document the protect manager should review?A . Project scheduleB . Action itemsC . Project charterD . Communication planView AnswerAnswer: A
Which of the following documents will the company MOST likely release FIRST?
A company has determined it does not have the in-house capability to perform a project and wants to procure third-party services. Which of the following documents will the company MOST likely release FIRST?A . RFOB . RFIC . RFPD . RFQView AnswerAnswer: B Explanation: References: Kim Heldman, CompTIA Project+ Study...
Which of the following shows projected project expenditures?
Which of the following shows projected project expenditures?A . Work breakdown structureB . Cash flow scheduleC . Cash burn rateD . Budget milestoneView AnswerAnswer: A
Which of the following should the project manager do to obtain the resources?
The project sponsor has cut the resources required for project completion. The project manager cannot complete the project without additional resources. Which of the following should the project manager do to obtain the resources?A . The project manager should identify and document the reasons for the additional resources in a...
Which of the following is a necessary step to record the actual durations?
A project manager needs to track the actual and estimated start and finish dates of all WBS work packages. Which of the following is a necessary step to record the actual durations?A . Establish each WBS work package resource.B . Establish and set the baseline.C . Establish and set the...
Which of the following phases does this describe?
A project manager is working on the project charter. Which of the following phases does this describe?A . InitiationB . PlanningC . ExecutionD . ClosingView AnswerAnswer: A Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 107
Which of the following risk strategies should the project manager adopt?
A project manager has an opportunity to add a highly skilled expert to the team who can increase the probability of the project’s success. Which of the following risk strategies should the project manager adopt?A . ExploitationB . AvoidanceC . AcceptanceD . MitigationView AnswerAnswer: A Explanation: References: Kim Heldman, CompTIA...