The Control Plan is the road map to sustaining the improvements made through the Lean Six Sigma project and should therefore involve keeping the __________ up to date as a means of supporting the Response Plan.

The Control Plan is the road map to sustaining the improvements made through the Lean Six Sigma project and should therefore involve keeping the __________ up to date as a means of supporting the Response Plan.A . X-Y DiagramB . Shewhart ChartC . FMEAD . Customer Service Plan View Answer Answer: C...