Scrum requires that the Product Owner must use which of the following items? (Choose all that apply)

Scrum requires that the Product Owner must use which of the following items? (Choose all that apply)
A . Burndown chart.
B . Feature bum-up.
C . Critical Path Analysis.
D . Project Gantt chart.
E . None of the above.

Answer: E

Latest PSPO-I Dumps Valid Version with 481 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments