A Scrum Master is keeping a list of open impediments, but it is growing and he/she has been able to resolve only a small portion of the impediments.
Which three techniques would be most helpful in this situation? (Choose three.)
- A . Consulting with the Development Team.
- B . Prioritizing the list and working on them in order.
- C . Arranging a triage meeting with all project managers.
- D . Alerting management to the impediments and their impact.
A product Increment must be released to production at the end of each Sprint.
- A . True
- B . False
If burndown charts are used to visualize progress, what do they track?
- A . Accumulated cost.
- B . Individual worker productivity.
- C . Work remaining across time.
- D . Accumulated business value delivered to the customer.
How is management external to the Scrum Team involved in the Daily Scrum?
- A . The Scrum Master speaks on their behalf.
- B . The Development Team self-manages and is the only management required at the Daily Scrum.
- C . Management gives an update at the start of each Daily Scrum.
- D . The Product Owner represents their opinions.
To get started in terms of what to build, Scrum requires no more than a Product Owner with enough ideas for a first Sprint, a Development Team to implement those ideas and a Scrum Master to help guide the process.
- A . True
- B . False
What is the time-box for the Sprint Review?
- A . As long as needed.
- B . 2 hours for a monthly Sprint.
- C . 4 hours for a monthly Sprint.
- D . 4 hours and longer as needed.
- E . 1 day
Who is responsible for tracking the remaining work of the Sprint?
- A . The Development Team.
- B . The Scrum Master.
- C . The Project Manager.
- D . The Development Team is consultation with the Product Owner.
- E . The Product Owner.
What is the tactic a Scrum Master should use to divide a group of 100 people into multiple Development Teams?
- A . Create teams based on their skills across multiple layers (such as database, UI, etc.)
- B . Ask the Product Owner to assign the people to teams.
- C . Ask the developers to divide themselves into teams.
Which statement best describes a Product Owner’s responsibility?
- A . Optimizing the value of the work the Development Team does.
- B . Managing the project and ensuring that the work meets the commitments to the stakeholders.
- C . Directing the Development Team.
- D . Keep stakeholders from distracting the Development Team.
The Sprint Review is mainly an inspect and adapt opportunity for which group?
- A . The Development Team and stakeholders.
- B . The Product Owner and Development Team.
- C . The Scrum Team and stakeholders.
- D . The Product Owner and management.
- E . The Development Team and management.
- F . The Product Owner and stakeholders.
63, 123: sprint goal
Qestions 63 and 123: Which output from Sprint Planning provides the Development Team with a target and overarching direction for the Sprint?
Answer to 63: Sprint Backlog
Answer to 123: Sprint Goal
Same question, different answers. Which answer is correct?
Hi, there is an issue in #67, please review:
67. What are two good ways for the Development Team to make non-functional requirements visible? (Choose two.)
1 Put them on a separate list on the Scrum board, available for all to see.correct
2 Add them to the Product Backlog and keep the Product Owner posted on the expected effort.correct
3 Run the integration and regression tests before the end of the Sprint, and capture the open work for the Sprint Backlog of the next Sprint.wrong
4 Add them to the definition of “Done” so the work is taken care of every Sprint.
I`ve chosen last two, but is says that #3 is incorrect. Then what 2 answers are correct?
Thanks!
bbbbb