In which phase of the protect design would an ICT distribution designer be expected to prepare preliminary cost estimates?

In which phase of the protect design would an ICT distribution designer be expected to prepare preliminary cost estimates?
A . CD
B . SD
C . PD
D . DD

Answer: B