Improvements that are outcome of the sprint retrospective can be added to the sprint backlog for the next sprint.

Improvements that are outcome of the sprint retrospective can be added to the sprint backlog for the next sprint.
A . True
B. False

Answer: A

Explanation:

The scrum guide says: "The most impactful improvements are addressed as soon as possible. They may even be added to the Sprint Backlog for the next Sprint."