If the probability and consequence combination (risk) is high enough to be unacceptable, then
If the probability and consequence combination (risk) is high enough to be unacceptable, then
A . A mitigation action to predict or prevent the eventis recommended.
B . A mitigation action to predict or prevent the event isnot recommended
C . Warrant to analyze risks involved
Answer: A