How should the administrator connect the switches for the best latency and load-balancing?

Refer to the exhibit.

A network administrator wants to create a leaf and spine topology.

How should the administrator connect the switches for the best latency and load-balancing?
A . Connect each leaf switch to each spine switch, and run a protocol such as EV
C . Connect each leaf switch to half of the spine switches, and run a protocol such as TRIL
E . Connect each leaf switch to each spine switch, and run a protocol such as TRIL
G . Connect each leaf switch to half of the spine switches, and run a protocol such as EV

Answer: C