During which phase of disaster recovery planning should an organization identify the business units, assets, and systems that are critical to continuing an acceptable level of operations?
During which phase of disaster recovery planning should an organization identify the business units, assets, and systems that are critical to continuing an acceptable level of operations?
A . Scope and initiation phase.
B . Business impact analysis.
C . Plan development.
D . Testing.
Answer: B