Cleveland brought the case to the court and sought rescission of contract with Digital. Is Cleveland’s claim appropriate in this case?

Cleveland Insurance (Cleveland) offers a range of insurance services. The main software used in the call centre is a customer relationship management (CRM) system. Cleveland perceived an urgent need to replace the existing CRM system to deal with the increasing number of customers and services.

Urgent Digital Ltd (Digital) is one of the bidders of Cleveland’s ITT for designing, building and managing the new CRM system. Its bid team is led by Hank Irvine, its technical director. Hank realises that winning the Cleveland contract (valued at approximately £50M) will enhance his career. During discussions with Cleveland, Hank offers certain assurances regarding timescales for the project. He has not carried out any investigations into the viability of the timescales. Hank has little idea whether the timescales can be met.

Cleveland decides that Digital’s bid meets with its requirements, especially given the assurances in timescale offered by Hank, and decides to proceed with it, subject to a formal contract. Eventually, a formal contract is signed by both parties. The initial assurances given by Hank about the timing of the project are never going to be achieved and are at best grossly exaggerated.

Cleveland brought the case to the court and sought rescission of contract with Digital. Is Cleveland’s claim appropriate in this case?
A . Yes, because Cleveland needs to seek rescission first before claiming for damages
B. Yes, because both parties agreed with rescission of their contract
C. No, because the work had been carried out which could not be returned
D. No, because the contract does not include any provision on rescission

Answer: C

Explanation:

Hank’s pre-contractual assurances may amount to misrepresentation. Remedies for misrepresentation could be rescission of contract or damages.

Rescission will be impossible in the following instance:

– Where the innocent party has affirmed the contract; that is, acted in a way confirming that they wish it to continue

– Where the claim has not been brought within a reasonable time (this is a point of general law)

– Where restitution (returning to the pre-contractual position) is impossible (e.g. because the goods have been consumed or have deteriorated)

– Where there has been intervention of innocent third-party (e.g., if the goods have been sold on)

In this case, the subject of contract is designing, building and managing the new CRM system which is impossible to be restituted. Therefore, the contract cannot be rescinded.

Reference: CIPS study guide page 53-55

LO 1, AC 1.2

Latest L4M3 Dumps Valid Version with 193 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments