The primary work products of the rbi assessment and management approach and implementation of rbi provides
The primary work products of the rbi assessment and management approach and implementation of rbi provides
A . Overall reduction of risk and acceptance of current risk
B . Overall increase of risk and acceptance of risk
C . Overall reduction of risk and negligence of current risk
D . Overall increase of risk and negligence of current risk
Answer: A