The following assumption can bemade that significantly impact the calculated corrosion rate early in the equipment life
The following assumption can bemade that significantly impact the calculated corrosion rate early in the equipment life
A . If the base line thickness were not performed the nominal thickness may be used for the original thickness
B . If original thickness not available, averaged ut thickness readings may be used
C . If the original thickness not available, maximum utthickness readings may be used
Answer: A