What does it mean when you set a work order task as an upstream task?

What does it mean when you set a work order task as an upstream task?
A . The downstream task must he approved before completing an upstream task
B . The task must he completed before any downstream tasks can be started
C . The task is dependent on another work order request
D . The task cannot he started until any upstream tasks have been completed

Answer: B