Which of the following would BEST determine whether a post-implementation review (PIR) performed by the project management office (PMO) was effective?
Which of the following would BEST determine whether a post-implementation review (PIR) performed by the project management office (PMO) was effective?
A . Lessons learned were implemented.
B. Management approved the PIR report.
C. The review was performed by an external provider.
D. Project outcomes have been realized.
Answer: D