With which field do you control the creation of a scheduling agreement with release documentation? Please choose the correct answer.
With which field do you control the creation of a scheduling agreement with release documentation? Please choose the correct answer.
A . Document Type
B . JIT Indicator
C . Item Category
D . Release Creation Profile
Answer: A