Which of the following elements can be generated by material requirements planning (MRP)? There are 3 correct answers to this question.

Which of the following elements can be generated by material requirements planning (MRP)? There are 3 correct answers to this question.
A . Production order
B . Purchase requisition
C . Delivery schedule line
D . Planned order O Purchase order

Answer: B,C,D