Why would vRealize Operations report that the cluster has 0 days remaining when the actual CPU overcommit ratio is less than the 4:1 configured value?

An administrator has enabled the allocation model in a policy and set the CPU overcommit ratio to 4:1 for all vSphere clusters in a vSphere datacenter.

Why would vRealize Operations report that the cluster has 0 days remaining when the actual CPU overcommit ratio is less than the 4:1 configured value?
A . The allocation model will always report zero remaining capacity when the actual ratio is less than the configured ratio.
B. The allocation model does not account for powered off virtual machines.
C. The CPU demand in the cluster is less than the total CPU capacity.
D. The CPU demand in the cluster is greater than the total CPU capacity.

Answer: D