Which two steps should be taken to prepare for this task?

An administrator needs to relocate an AHV cluster to a new datacenter during a maintenance window. The cluster will use the same IPs in the new datacenter.

Which two steps should be taken to prepare for this task? (Choose two.)
A . Reconfigure IPMI for the new datacenter
B . Shut down all user VMs in the cluster
C . Relocate the linked LDAP server
D . Stop all Nutanix Files clusters

Answer: C,D